Grid connection and smart meter : the complete guide
You’ve completed your snagging inspection, the defects are being resolved, and now you need electricity — not the temporary site supply, but the permanent grid connection with a Linky smart meter. This step, often delayed due to a lack of clarity, is critical: without it, no heating, no compliance certificate, no moving in. This guide walks you through every step of the Enedis connection process — from the online application to supply activation — with realistic timelines, costs and pitfalls to avoid.
Enedis is the French Distribution Network Operator (DNO), equivalent to your regional DNO in the UK (e.g. UK Power Networks, Western Power Distribution). All new electricity connections in France go through Enedis.
Grid connection with Enedis: the 6 detailed steps
Step 1 — The connection application
The application is submitted directly on enedis.fr (under “Raccordement”) or by post. You will need to provide:
- The planning permission (copy of the decision notice)
- The site plan showing the desired location of the meter box
- The required power rating (12 kVA single-phase for a standard house, 36 kVA three-phase if you have a powerful heat pump or large workshop)
- Your contact details and the desired supply activation date
Tip — Submit your connection application as soon as planning permission is granted, even if the build hasn’t started yet. Enedis lead times are long (2 to 6 months for the works), and you don’t want the grid connection to be the bottleneck at the end of the project. Ideally, submit the application at the time of groundworks and utilities so the trench can be dug at the same time.
Step 2 — The connection offer (PDR)
Enedis reviews your application and sends you a connection offer (PDR — Proposition de Raccordement) within approximately 6 weeks. This document includes:
- The technical description of the connection (connection type, cable length, power rating)
- The detailed quote for works covered by Enedis and works at your cost
- The estimated completion timeline
- The payment terms
The connection offer is valid for 3 months. Paying it constitutes acceptance and triggers the scheduling of works.
How much does it cost?
The cost depends on the distance between the existing network and your plot. Enedis applies a regulated tariff scale:
| Situation | Indicative cost (excl. VAT) |
|---|---|
| Network at plot boundary (< 30 m) | €1,000 to €2,500 |
| Network extension required (30–200 m) | €2,500 to €8,000 |
| Remote network (> 200 m) or rural area | €8,000 to €25,000+ |
| Three-phase instead of single-phase | Additional ~€500 |
These amounts cover works from the public network up to the meter box at the property boundary. The cable between the meter box and your house (the “service cable”) is your responsibility — budget €500 to €2,000 depending on the distance.
Warning — If your plot is in a rural area or far from the network, connection costs can be very high. This is a point to check before buying the land — see our guide on land viability analysis and utility connections.
The Consuel certificate: a mandatory step before supply activation
The Consuel (Comite National pour la Securite des Usagers de l’Electricite) issues the electrical compliance certificate for your installation. This document proves that your installation meets the NF C 15-100 standard — the French equivalent of BS 7671 / IET Wiring Regulations in the UK. Without a Consuel certificate, Enedis will not activate the supply.
In the UK context, the nearest equivalent is a Part P Building Regulations compliance certificate or an Electrical Installation Certificate (EIC) to BS 7671.
How to obtain the Consuel certificate
- Order the form on consuel.com — cost: approximately €130 incl. VAT (2025 rate for a detached house, yellow Cerfa form)
- Complete the declaration (or have your electrician complete it) with the installation details
- Send the form to your regional Consuel office
- Inspector visit (in some cases) — they carry out an on-site compliance check
- Receipt of the endorsement: if everything is compliant, Consuel endorses the certificate within ~7 working days

Will an inspector come to visit?
Not automatically. Consuel operates by sampling: approximately 30 to 40% of new installations are subject to a visit. If you are selected:
- The inspector checks the consumer unit, earthing, bathroom zones, and cable cross-sections
- If the installation is compliant → immediate endorsement
- If non-conformities are found → you receive a report listing the points to correct. You must make corrections, then request a second visit (additional cost may apply)
Best practice — Before submitting to Consuel, carry out your own (or with your electrician) a thorough pre-check: test the RCDs, measure the earth resistance (< 100 ohms), check bathroom zones, label the consumer unit. A Consuel rejection costs you 2 to 3 weeks minimum — best avoided.
The most common reasons for rejection
| Reason for rejection | Detail |
|---|---|
| Earth resistance out of tolerance | Resistance > 100 ohms (measured value too high) |
| Faulty RCD | The 30 mA RCD does not trip on test, or is not Type A for dedicated circuits |
| Bathroom zones not respected | Socket or switch in zone 0 or 1 |
| Consumer unit not labelled | Circuits not identified, single-line diagram absent |
| Inadequate cable cross-section | 1.5 mm² cable on a 20A circuit (sockets) instead of 2.5 mm² |
| Equipotential bonding | Missing bonding in the bathroom |
Single-phase or three-phase: which to choose?
In summary:
- Single-phase 12 kVA: sufficient for 80% of detached houses. Heating by stove, modest heat pump, no heavy electrical equipment. Subscription ~€180/year.
- Three-phase 36 kVA: required if you have a powerful heat pump, a workshop (table saw, planer-thicknesser), or if you plan a solar self-consumption installation > 6 kWp. Subscription ~€320/year.
Tip — If in doubt, go single-phase 12 kVA — it’s simpler and cheaper. You can always request an upgrade to three-phase later (Enedis intervention cost approximately €150). The reverse is also possible. But make sure to size the service cable correctly from the start (minimum 4 × 16 mm²) so you don’t have to dig up the trench again.
Supply activation: the final step
Once the Consuel certificate is obtained and the connection works are complete, all that remains is the supply activation.
Procedure
- Choose an electricity supplier: EDF, Engie, TotalEnergies, or any alternative supplier. The unit rate varies — compare offers on the official energy mediator comparison tool
- Take out a contract by providing: the endorsed Consuel certificate, your meter’s PDL supply number (Point De Livraison — the MPAN equivalent in the French system), and your required power rating
- The supplier passes the request to Enedis for supply activation
- Enedis activates the meter — with a Linky smart meter, this is done remotely within 24–48 hours. No site visit required.
Supply activation costs
| Type of activation | Cost (incl. VAT, 2025 rate) |
|---|---|
| Standard activation (within 5 working days) | ~€14 |
| Express activation (within 24–48 h) | ~€52 |
| Emergency activation (same day) | ~€172 |

Best practice — Start the supplier contract application as soon as you have the endorsed Consuel certificate in hand. Standard activation (€14) takes 5 working days — if you’re in a hurry to move in, the express option (€52) saves you 3–4 days. The emergency option is rarely needed.
The temporary site connection
During the build, you probably used a temporary site connection (site meter). Here are the differences:
| Temporary (site) | Permanent (residential) | |
|---|---|---|
| Power rating | 12 to 36 kVA | 6 to 36 kVA |
| Duration | 12 months max (renewable) | Permanent |
| Consuel | Not required | Mandatory |
| Meter | Site meter on a post | Linky in meter box |
| Tariff | Often higher (site tariff) | Regulated rate or market offer |
At the end of the build, the temporary connection is removed and replaced by the permanent connection. If you planned ahead by having the permanent meter box installed from the start, the transition is quicker.
Common pitfalls and how to avoid them
1. Forgetting the trench
The Enedis cable runs underground in a trench 80 cm deep between the network and the meter box. If you are doing your own groundworks, plan this trench from the earthworks stage — otherwise Enedis will charge separately for it, and it’s expensive (€30 to €50 per linear metre).
2. Positioning the meter box incorrectly
The meter box must be:
- At the property boundary, accessible from the public highway
- At a regulation height (between 0.50 m and 1.50 m from the ground)
- Recessed or free-standing, according to the local network operator’s specifications
Warning — If the meter box is incorrectly positioned (too far from the public highway, not accessible, wrong height), Enedis may refuse to connect or require repositioning at your cost. Confirm the location with Enedis before casting the base.
3. Under-sizing the service cable
The cable between the meter box (at the boundary) and the consumer unit (inside the house) is your responsibility. It must be correctly sized:
| Power rating | Copper cross-section | Aluminium cross-section |
|---|---|---|
| 12 kVA single-phase | 2 × 16 mm² | 2 × 25 mm² |
| 36 kVA three-phase | 4 × 16 mm² | 4 × 25 mm² |
Bury it in a red TPC duct at a minimum depth of 80 cm, with a red warning mesh above it. Plan generously — a cable that is too short or too small means digging up the trench again.
4. Confusing the PDL number and the PRM number
- PDL (Point De Livraison): the old identifier (14 digits), still used by some suppliers — roughly equivalent to an MPAN in the UK
- PRM (Point Reference Mesure): the new Linky identifier (also 14 digits)
In most cases, PDL = PRM for a new installation. You will find it on your Enedis connection offer or on the Linky meter once installed.
Timelines: a realistic schedule
| Step | Average lead time | Tip to speed things up |
|---|---|---|
| Application → connection offer received | 6 weeks | Submit a complete application first time |
| Connection offer accepted → works | 2 to 6 months | Apply as soon as planning permission is granted |
| Enedis works | 1 to 3 days | Trench already dug by you |
| Consuel (submission → endorsement) | 7 to 15 days | Pre-check before submitting |
| Linky supply activation | 24 h to 5 days | Express option if in a hurry |
| Realistic total | 3 to 8 months | Start at the beginning of the structural works |
Warning — Enedis lead times vary significantly by region and local workload. In high-pressure areas (Paris region, major cities), 6 months is common. In rural areas requiring network extension, it can exceed 12 months. Plan ahead.
Checklist: Enedis grid connection and Linky smart meter
- Connection application submitted on enedis.fr (as soon as planning permission is granted)
- Site plan with meter box location submitted
- Power rating chosen (single-phase 12 kVA or three-phase 36 kVA)
- Connection offer (PDR) received and reviewed
- Connection offer paid within the 3-month validity period
- Trench prepared (80 cm deep, red TPC duct, warning mesh)
- Meter box positioned at property boundary (height 0.50–1.50 m)
- Service cable sized and installed (meter box to consumer unit)
- Electrical installation complete and compliant with NF C 15-100
- Consuel form ordered and completed (yellow Cerfa, ~€130)
- Pre-check carried out (earth resistance, RCDs, bathroom zones, labelling)
- Consuel endorsement received
- Electricity supplier chosen (compare on energie-info.fr)
- Contract taken out with PRM number and Consuel certificate
- Supply activation confirmed — Linky smart meter active